A remote audit of Uzbekistan’s 2025 regional infrastructure programmes has found that more than a third of facilities officially recorded as commissioned never had their acceptance documents entered into the state’s transparency platform — a gap that auditors say undermines accountability for tens of trillions of soums in public spending.

The Chamber of Accounts conducted the review in the first quarter of 2026, examining five state programmes that together allocated 32.2 trillion soums for 9,066 projects across the country’s social and productive infrastructure. According to official reports submitted to the audit, 28.1 trillion soums — 87 percent of the allocation — was absorbed, 28.6 trillion soums (89 percent) was formally financed, and 7,553 facilities were brought into operation.

What Was Built

The commissioned facilities span a wide range of public services. In the social sector, 1,144 general-education and creative schools were opened alongside 286 kindergartens, 334 medical institutions, 123 higher-education, science and innovation facilities, and 178 sports and cultural venues. Engineering and utility infrastructure accounted for the bulk of the remaining completions: 2,399 road infrastructure objects, 1,123 irrigation and land-reclamation structures, 951 electricity-supply improvements, 259 drinking-water and sewerage facilities, 502 architectural and landscaping projects, 31 heat-supply objects, six gas-supply objects, three railway and metro objects, and 214 other facilities where construction, repair or fitting-out work was carried out before commissioning.

Where the System Broke Down

Despite the headline completion figures, the Chamber of Accounts identified a series of systemic failures. Across 250 projects, financing was never opened and construction never began. The most common reason was the absence of expert conclusions, which blocked 167 objects. Contractors or suppliers had not been selected for 60 projects; project and cost documentation had not been prepared for 14; six objects were declared unpromising by local hokimiyats and kengashes; and three sites were stalled because the land-use category had not been changed.

A separate planning failure affected 89 carry-over projects that had been included in the 2025 programme but were not carried forward into the 2026 programme, leaving their completion status unresolved.

The most striking finding concerns documentation. Although 7,553 facilities are reported as commissioned in 2025, acceptance acts for 2,663 of them — 36 percent of the total — have not been entered into the Transparent Construction platform. The omission means that more than one in three officially completed objects lacks a verifiable digital record of handover.

The Chamber forwarded its recommendations to the Presidential Administration, and the Cabinet of Ministers subsequently issued specific instructions to the relevant ministries and agencies. Auditors called for a joint review of the list of unfinished objects and measures to complete them under the 2026 programme, a full inventory of all projects implemented under the programmes, completion of outstanding acceptance documentation, and comprehensive data entry into both the Transparent Construction and Capital Investments information systems. To sharpen ministerial accountability going forward, the Chamber also recommended introducing an automatic KPI rating system to track compliance with programme targets and deadlines.