An efficiency audit of public funds allocated to Tashkent region’s social and industrial infrastructure development programme for 2023–2024 has uncovered design errors in project documentation and a systemic failure to formally transfer completed facilities to their operating organisations, Uzbekistan’s Chamber of Accounts reported on 9 October 2025.

Auditors found that project documentation prepared for two specific schemes — the construction and reconstruction of sewage treatment facilities in the city of Krasnogorsk in Parkent district, and the construction of an amphitheatre in Yangi O’zbekiston park alongside an artificial lake at Nurafshon Business City — contained incorrect references to urban planning norms and included work categories that did not belong in the specifications. The Chamber of Accounts said these errors were corrected during the audit period.

Completed Buildings Left in Administrative Limbo

A more widespread problem concerned the handover of finished infrastructure. According to state acceptance commission records, 58 facilities commissioned in 2023 and 2024 were not transferred to their designated user organisations on time. The audit found they were eventually transferred during the review period, but the delay represents a gap in accountability: assets built with public money sat outside any organisation’s formal balance sheet, leaving maintenance responsibilities and ownership unclear.

The regional hokimiyat’s Capital Construction Client Service managed to bring 36 previously overdue facilities into operation during the audit window, suggesting the review itself prompted administrative action.

Scale of Construction Delivered

The audit also documented what the programme did achieve. Three new schools providing 958 places were built, and 51 existing general-education schools accommodating 24,410 pupils were reconstructed. In early-years education, three new preschool institutions with 390 places were constructed and 12 were reconstructed, adding capacity for a further 2,040 children.

Healthcare infrastructure saw four new family polyclinics built with a combined daily capacity of 700 visits, while eight existing family polyclinics and a number of treatment-and-prevention facilities were reconstructed to handle an additional 1,135 visits per day.

Water and sanitation works were substantial in scale: 1,448 kilometres of drinking-water pipeline were laid alongside 217 kilometres of sewage network, and a wastewater treatment plant with a capacity of 4,000 cubic metres per day was commissioned. Road works covered 628 kilometres of public roads and 1,715 kilometres of internal neighbourhood roads across the region.

The Chamber of Accounts said it had issued recommendations to the relevant state bodies to address the conditions that produced the identified shortcomings.