Uzbekistan’s Accounts Chamber has completed an audit of the Ministry of Water Resources, finding that contractors were selected late, canal reconstruction projects went unfinished, drip-irrigation equipment sat unused, and private partners operating state pump stations faced no meaningful oversight — all problems the auditors traced to systemic management failures rather than isolated lapses.
The audit, published on 3 October 2025, examined how the ministry had carried out tasks assigned at a presidential video-conference on 7 November 2024. Auditors concluded that while the tasks were formally tracked, those whose deadlines had passed had not been fully completed.
Canal Reconstruction Stalled From the Start
A separate efficiency audit, conducted under Presidential Decree No. PP-454 of 26 December 2024, scrutinised funds allocated for canal reconstruction in 2025. It found that the Council of Ministers of the Republic of Karakalpakstan and the regional hokimiyats — the provincial administrations responsible for selecting contractors — delayed those selections by between 10 and 69 days. Despite concrete lining work having begun in the first quarter of 2025, not a single facility had been handed over for operation by the time of the audit.
The review of water-saving technology deployment found instances where drip-irrigation systems had been installed but were not in use — a finding that points to a gap between procurement and actual agricultural practice.
PPP Pump Stations Left Without Scrutiny
Between 2020 and 2025, the Ministry of Water Resources transferred a number of pump stations to private partners under public-private partnership agreements, on the condition that those partners would modernise the facilities and manage them efficiently. The Accounts Chamber found that the ministry had not carried out the required biannual monitoring of work performed under those agreements and had not obtained documented confirmation of what the private partners had actually done.
Auditors also identified the absence of any established procedure for setting minimum investment thresholds or energy-saving requirements when structuring PPP projects — meaning private partners faced no binding baseline for how much they were obliged to invest or how much energy they were expected to save.
Digital Systems Functioning Only Partially
An analysis of the ministry’s digitalisation programme — covering the automated monitoring of water resources, electricity consumption and water-management infrastructure — found that the information systems developed for the sector were not yet fully operational.
The Accounts Chamber said it had issued recommendations to the relevant organisations to address each of the shortcomings identified. No figures were given for the total value of funds audited or for any financial losses, and no disciplinary or legal proceedings were announced in the audit findings.